Saturday, September 21, 2013

This week the team worked on the design of the system and the SRS document.

As a team:
  • We hashed out the overall design of the system (2 hours)
  • Finished the SRS document (3 hours)
  • Setup GitHub (10 minutes)

As Individuals we:
  • Each did prototypes of the views using the pencil project (2 hrs/person)
  • Designed individual UI’s to be compared as a group (2 hrs/person)

We also scheduled the following for this week:

  • Rob: Start working on the code for the login page
  • Paul: Start working on the toolbar (buttons, images and memento)
  • Andrew: Start looking into the database
  • Nsama: Start working on the data structures
  • Eric: Start working on the standard layout menu

Saturday, September 7, 2013

9/7/2013 Blog entry # 1

What did we do this week?
Group
  • General design meeting -1hr
  • Met each other and exchanged contact info - 30min
  • Won in class activity - 1hr
  • Merged individual UI ideas - 1hr
  • Spoke to user for initial requirements and designs - 1hr

Individual
  • Paul - Member view design - 1hr
  • Robert - Experimental GUI design -1hr
  • Andrew - Equipment view design-1hr
  • Nsama - Classes view design-1hr
  • Eric - leagues view design-1hr

Next Week
  • Standardized window design - 1hr
  • Create a prototype interface document - 2hr
  • Cover prototype document with user - 1hr
  • Work on SRS document - 2hr